Four Mile Parkway & US 50 Intersection

Owner: Four Mile Ranch Development Co.
Engineering Firm: MVE

This project started in early May and we are expected to be completed by the third week of July of 2006. This project consists of the following: Clear and Grubbing, Road Base Material, Acel/Decel Lanes, and Traffic Signal Lights. Colorado Department of Transportation has a part-time inspector involved with this project since it is a right-of-way access improvement project. Danny Tezak is the Project Manager on this project. All earthwork, paving, striping, and guardrail have been completed as of June 30, 2006. This Project was completed and traffic was placed on it's final alignment as of July 28 2006.

Four Mile Parkway & US 50 Intersection