US 50 - Critical Culvert Repair Project
Owner: Colorado Department of Transportation, Region 2, North Program
Prime Contractor: Rocky Mountain Materials
Project Location: Located on US 50 between Penrose and Canon City, CO.
Project Description:
We have been subcontracted by Rocky Mountain Materials to perform the following subcontract work: 188 CY's of 12" Rip Rap, 375 CY's of 18" Rip Rap for Abutment Protection, 150 CY's of 24" Rip Rap, 54-Inch Culvert Lining, 72-Inch Culvert Lining, Removal and replacement of exisisting headwall and wingwalls, 892 LF of 48" Reinforced Concrete Pipe, and 315 LF of 72" Reinforced Concrete Pipe.