Homestake Arkansas River Diversion – Drop 8:
Project Owner: Colorado Springs Utilities
Tezak Heavy Equipment:
Overall Manager: Danny Tezak
Engineer/Estimator: Bryan Danner
Health and Safety Manager: Dean Burns
Project Manager: Brandon Houser
General Superintendent: Troy Adair
Project Superintendent: Keith Martinez
Description of Project: The Arkansas River Diversion project was completed by Tezak Heavy Equipment in 2019. Colorado Springs Utilities contracted Tezak Heavy Equipment for additional work which included the construction of an additional drop 8, adjustment to the concrete apron of drop 2 in the boat chute, revegetation, highway entrance improvements and signs.
Project Major Activities:
- EROSION & SEDIMENT CONTROL
- BOAT CHUTE DROP 2 ADJUSTMENTS
- DEWATERING, DIVERSION & CARE OF WATER
- VOID FILLED RIPRAP/EXCAVATION
- GROUTED RIPRAP/EXCAVATION
- REVEGETATION
Project Location: Buena Vista, CO
Contract Amount at Award: $375,185.51
Final Contract Amount: $422,037.22
Anticipated Start Date: 03/16/2020
Start Date: 8/17/2020
Anticipated End date: 05/15/2020
Actual End Date: 09/28/2020
Subcontractors: Desert Creek Pumping, Edward James Surveying, Ground Engineering Consultants, Garney Construction, Hydro Turf