DW Eleven Mile Reservoir Outflow Flume Replacement
Project Owner: Board of Water Commissioners
Tezak Heavy Equipment:
Overall Management: Danny Tezak
Engineer/Estimator: Bryan Danner
Health and Safety Manager: Dean Burns
Project Manager: Ben Borton
General Superintendent: Troy Adair
Project Superintendent: Sean Webb
Description of Project:
- Demolition of existing concrete flume and stilling well.
- Design, installation, and maintenance of temporary river diversion and dewatering systems.
- Construction of a replacement concrete flume and stilling well.
- Relocation of existing precast concrete gage house on new foundation slab.
- Site earthwork and rip rap armoring of riverbanks.
Project Major Activities:
- EROSION CONTROL
- DEMOLITION/MASS EX-FLUME
- SALVAGE GAGE HOUSE FOR RESET
- WATER CONTROL AND DEWATERING
- STREAMBANK RIPRAP
- RIPRAP RESTORATION (75 CY PER NOTE)
- STR EX/ SUBGRADE PREP
- STILLING WELL
- CONCRETE FLUME
- ALUMINUM FOOTBRIDGE
- STRUCTURE BACKFILL
- RESET PRECAST GAGE HOUSE
- NEW RIPRAP
- BOULDERS AT TOE OF NEW RIPRAP
- SEEDING/FINAL STABILIZATION
- ELECTRICAL
Project Location: Park County, CO
Contract Amount at Award: $779,810.00
Final Contract Amount: $788,855.45
Start Date: 8/17/2020
Anticipated End date: 12/18/2020
Actual End Date: 11/18/2020
Subcontractors: Hydro-Turf, Inc., M & S Trucking, Edward-James Surveying, Ground Engineering, Main Electric, Montano Concrete, and Work Zone Traffic Control