US50B Scour Critical Countermeasures
Description of Project: This was a scour countermeasure project under CDOT structures: K-18-BY & K-18-BZ on US50B at MP 318 on the east side of Pueblo, Colorado. Project work consisted of repairing existing scour with fill material and constructing a scour preventative grouted boulder drop structure.
Project Owner: Colorado Department of Transportation
Tezak Heavy Equipment:
Overall Management: Danny Tezak
Engineer/Estimator: Bryan Danner
Health and Safety Manager: Dean Burns
Project Manager: Brandon Houser
General Superintendent: Troy Adair
Project Superintendent: Keith Martinez
Project Major Activities:
- UNCLASSIFIED EXCAVATION
- EMBANKMENT MATERIAL
- BLADING
- DOZING
- COMBINATION LOADER
- STRUCTURE EXCAVATION
- STRUCTURE BACKFILL
- TOPSOIL
- STOCKPILE TOPSOIL
- EROSION LOG
- ROCK CHECK DAM
- EROSION CONTROL MANAGEMENT
- WATER CONTROL
- SEEDING
- SOIL CONDITIONING
- MULCHING
- MULCH TACKIFIER
- SOIL RETENTION BLANKET
- GEOTEXTILE
- STEEL SHEET PILING
- SOIL RIPRAP
- GROUTED RIPRAP SLOPE AND DITCH PAVING
Project Location: Pueblo County
Contract Amount at Award: $570,845.95
Tentative Start Date: September 10, 2020
Actual Start Date: September 10, 2020
Anticipated End date: November 30, 2020
Actual End Date: Novemember 7, 2020
Subcontractors: Ground Engineering, Mod Squad, Edward James Surveying, Smelker Concrete, T-P Enterprises, The Idea Marketing