Sunburst Trail Pipe Repair Project

Project Owner: Douglas County Government,100 Third Street, Suite 220, Castle Rock, Co 80104

 

Tezak Heavy Equipment:
Overall Management: Danny Tezak

Engineer/Estimator: Bryan Danner

Health and Safety Manager: Dean Burns

Project Manager: Ben Borton 

General Superintendent: Troy Adair

Project Superintendent: Sean Webb

 

Description of Project: This project is a culvert slip lining including erosion control, landscaping, soil riprap, concrete walling, annular space grouting, culvert lining and traffic control.

 

Project Major Quantities:

CLEARING AND GRUBBING

REMOVAL OF TREE

REMOVAL OF PIPE

CLEAN CULVERT

SEDIMENT CONTROL LOG (12 INCH)

SILT FENCE

CONCRETE WASHOUT STRUCTURE

VEHICLE TRACKING CONTROL     

SWEEPING (SEDIMENT REMOVAL)

SEEDING (NATIVE)

MULCHING (WEED FREE STRAW)

SOIL RIPRAP (18 INCH)

CONCRETE CLASS D (WALL)

ANNULAR SPACE GROUTING

CULVERT LINING (120 INCH)

FENCE (PLASTIC)

SANITARY FACILITY

MOBILIZATION

CONSTRUCTION TRAFFIC CONTROL

FORCE ACCOUNT - MINOR CONTRACT REVISION

 

Project Location: Douglas County

Contract Amount at Award: $231,144.90

Final Contract Amount: $231,144.90

Tentative Start Date: September 8, 2020

Actual Start Date: October 14th, 2020

Anticipated End date: August 31, 2021

Actual End Date: Pending

Subcontractors: Flashfill, M.L.L., Hydro-Turf, Work Zone

 

Northern Water Supply Project North Booster Pump Station Overflow Channel
Read more
Fountain Creek Stabilization at Hanson Trailhead Project
Read more
Templeton Gap @ Siferd Blvd. Stream Stabilization
Read more
Timber Ridge Multi-plate Structure, Sheetpile Check Structures and Channel Bank Stabilization
Read more