Williams Fork Dam Reservoir Access Improvements

Project Owner:   Denver Water

Tezak Heavy Equipment:

Overall Management: Danny Tezak
Engineer/Estimator: Bryan Danner

Health and Safety Manager: Dean Burns

Project Manager: Ben Borton           

General Superintendent: Troy Adair

Project Superintendent: Jesse Ellis

 

Description of Project:  The existing Williams Fork Dam Access Road runs to the west of Williams Fork Dam and Reservoir. A discrete portion of this roadway, along the left abutment, has exhibited deterioration due to subgrade material loss along a cut/fill portion of the roadway. To inhibit future material loss and allow full access of the roadway, a segmental block gravity retaining wall will be constructed. The proposed gravity wall improvements consist of removing the fill material along the slope adjacent to the roadway to competent rock and constructing a segmental block gravity retaining wall at the base of the slope excavation. The proposed gravity wall consists of 41-inch Redi-Rock Ledgestone blocks. A low strength backfill concrete and granular fill will be placed below the proposed roadway and used to fill between the gravity wall and adjacent rock slope. The low strength concrete backfill was selected to limit earth and surcharge lateral stresses from acting on the wall and will be placed in two lifts.  In addition, construction includes the installation of drainage pipe, concrete backfill material, bollards, final grading, and reinforcement appurtenances.

 

Project Major Activities:

MOBILIZATION                         

SURVEY / LAYOUT                    

EROSION CONTROL                  

SEEDING & RECLAMATION       

CONCRETE REPAIRS                 

EXCAVATION WALL                  

ANCHORS                                 

REDI ROCK RETAINING WALL   

DRAIN PIPE/DRAIN BOARD       

CONCRETE BACKFILL               

BOLLARDS 6" X 6' SCH  40        

FINAL GRADING                                   

                                                                                                                         

Project Location:  Grand County

Contract Amount at Award: $357,332.53

Final Contract Amount: pending

Start Date: October 11, 2021

Anticipated End date:  November 12, 2021

Actual End Date:  Pending

Subcontractors: Hydro Turf, Inc., Azimuth Survey Co.

21WPS Wilkerson Pass Safety Project
Read more
Williams Fork Dam Reservoir Access Improvements
Read more
Fountain Creek Stabilization at Hanson Trailhead Project
Read more
Templeton Gap @ Siferd Blvd. Stream Stabilization
Read more