Project Owner: Colorado Department of Transportation
Tezak Heavy Equipment:
Overall Management: Danny Tezak
Engineer/Estimator: Bryan Danner
Health and Safety Manager: Dean Burns
Project Manager: Brandon Houser
General Superintendent: Troy Adair
Project Superintendent: Keith Martinez
Project Major Activities:
- Unclassified Excavation
- Embankment Material
- Blading
- Dozing
- Combination Loader
- Structure Excavation
- Structure Backfill
- Topsoil
- Stockpile Topsoil
- Erosion Log
- Rock Check Dam
- Erosion Control Management
- Water Control
- Seeding
- Soil Conditioning
- Mulching
- Mulch Tackifier
- Soil Retention Blanket
- Geotextile
- Steel Sheet Piling
- Soil Riprap
- Grouted Riprap Slope and Ditch Paving
Project Location: Pueblo County
Contract Amount at Award: $570,845.95
Final Contract Amount: Pending
Tentative Start Date: September 10, 2020
Actual Start Date: September 10, 2020
Anticipated End date: November 30, 2020
Actual End Date: Pending
Subcontractors: Ground Engineering, Mod Squad, Edward James Surveying, Smelker Concrete, T-P Enterprises, The Idea Marketing